Construction Progress of the CENTRAL HILLS Residential Complex as of June 9, 2026
Construction Progress of the CENTRAL HILLS Residential Complex as of June 9, 2026
Slate Tower
Monolithic work is underway on the 18th floor.
Concrete has been poured for the wall and two elevator shafts, with a total volume of 17.6 m³. Work is also continuing on the concrete encasement of the areas around the ventilation units on the 14th and 15th floors.
Ruby Tower
Work is underway to build interior partitions and niches on the 25th floor.