Construction Progress of the Central Hills Residential Complex as of July 17, 2026
Construction Progress of the Central Hills Residential Complex as of July 17, 2026
At Slate Tower, monolithic construction work is underway on the 18th floor, and concrete has been delivered for the construction of the building's structural frame.
Window installation continues at Ruby Tower: double-pane windows have been installed from the 2nd to the 25th floor. Interior walls are being built on the 26th floor. Exterior and interior walls and partitions have been completed from the 2nd to the 25th floor.