Progress of construction of the Central Hills RC as of November 3, 2025

Progress of construction of the Central Hills residential complex as of 23 December 2025

Slate Tower
Concreting of the 15th floor slab completed (100%)
Reinforcement and concreting of vertical structures (walls and pylons) on the 16th floor continues (50%)

Ruby Tower
Window frames installed up to the 25th floor (inclusive)
Bricklaying of interior walls on the 23rd floor nearing completion
Preparations underway for bricklaying of interior walls on the 24th floor

See details in our new photo report from the construction site.