CENTRAL HILLS Residential Complex construction progress as of February 24, 2026

CENTRAL HILLS Residential Complex construction progress as of February 24, 2026

In the Slate Tower building of the CENTRAL HILLS RC, reinforcement of vertical elements (walls and pylons) on the 16th floor has been completed, and the formwork for the 16th-floor floor slab is being installed. Builders are currently pouring concrete for the walls and pylons of the 16th floor.

In the Ruby Tower building, masonry of internal walls is being carried out on the 24th floor.

See details in our new photo report from the construction site.