Hi friends! 🤗 Today we want to share with you an update from the CENTRAL HILLS construction site.
🏗️ Building 2:
• Work is currently underway on the installation of formwork for vertical elements (pylons) on the 4th floor.
🏗️ Building 3:
• Masonry of internal partitions on the 12th floor continues.
• Installation of ventilation units on the 25th floor is also underway.
Our company makes every effort to create a safe environment for everyone.