Work continues on reinforcing and concreting the floor slab of the 15th floor of the Slate Tower building in the CENTRAL HILLS residential complex. The installation of ventilation units and staircases is ongoing.
At Ruby Tower, the internal walls on the 23rd floor have been bricked up. Window frames have also been installed on the 23rd and 24th floors.