Construction progress of the Central Hills RC as of March 14, 2025
Construction progress of the Central Hills RC as of March 14, 2025
🏢Slate Tower
• Staircase formwork installation on the 12th floor.
• Staircase concreting on the 12th floor.
• 50% of the formwork for the 13th floor floor reinforcement has been installed.