Construction progress of the Central Hills RC as of February 7, 2025

Construction progress of the Central Hills residential complex as of February 7, 2025

🏢Slate Tower
• Concreting of pylons of the 11th floor is 90% completed.
• Formwork and floor reinforcement of the 12th floor are being installed.

For more information, contact the number: