Central Hills' traditional weekly construction report.
As of 07.07:
Building 2:
• Construction of the frame of the elevator shaft on the 3rd floor is in progress.
• Horizontal formwork for the ceiling of the 3rd floor is being installed
Building 3:
• Masonry of internal partitions and niches for communications on the 10th floor is in progress.