Construction progress of the Central Hills RC as of July 5, 2024

Construction progress of the Central Hills residential complex as of July 5, 2024

🏢Slate Tower
• The shields of the vertical formwork are being replaced for further pouring of the pylons and walls of the 9th floor.
• The walls of the 7th and 8th floors are being sanded and plastered.