Progress of construction of the Central Hills residential complex as of September 4, 2025
Progress of construction of the Central Hills residential complex as of September 4, 2025
🏢Slate Tower
• Ventilation units and staircases are being installed.
• Formwork for reinforcing the 15th floor slab is being installed.
🏢Ruby Tower
• Window frames are being installed on the 15th and 16th floors.
Bricklaying of the interior walls on the 21st floor is ongoing.