Construction progress of the Central Hills RC as of May 31, 2024

Construction progress of the Central Hills residential complex as of May 31, 2024

🏗️SLATE TOWER
• Completion of monolithic work on the floor of the 9th floor.
• Production of metal frames of the 9th floor has begun.

🏗️RUBY TOWER
• Concreting of the floor of the stairwell is underway.