Construction progress of the Central Hills RC as of August 30, 2024

Construction progress of the Central Hills residential complex as of August 30, 2024

🏢Slate Tower
• Reinforcement and installation of pylons on the 10th floor has been completed.
• Preparations for wall reinforcement are underway.