Progress of construction of the Central Hills residential complex as of November 3, 2025
Progress of construction of the Central Hills residential complex as of November 3, 2025
🏢 Slate Tower
• Installation of ventilation units on the 14th floor has been completed.
• Reinforcement and installation of vertical structures on the 15th floor has been completed.
• Concreting of the 15th floor pylons has been completed.
🏢 Ruby Tower
• External walls from the 20th to the 26th floor have been erected in the footnote areas.
• Materials for building internal walls on the 23rd floor have been delivered.
• Window frames have been installed up to the 20th floor.