Progress of construction of the Central Hills residential complex as of November 29, 2025

Progress of construction of the Central Hills residential complex as of November 29, 2025

🏢 Slate Tower
• Concrete pouring of vertical elements on the 15th floor is being completed.

🏢 Ruby Tower
• Window installation is underway on floors 21–22.
• Internal wall construction is being completed on the 22nd floor.