Construction progress of the Central Hills Residential Complex for January 28
🏗️ Building 1
• Electricity connection for the first stage of construction of building #1, sections 1-3;
• Fences were installed around the construction site for safe construction;
• Repair work in the sales department has been completed for a comfortable stay of investors at the construction site.
• Concreting of vertical structures (pylons, walls) is in progress, and work is underway to install the floor slab on the 26th floor.
• Bricklaying of internal walls and partitions on 3.4 floors is being carried out.
• Installation of prefabricated reinforced concrete structures (ventilation blocks and staircases) is in progress