November 14, 2023

Back

04022022_1
04022022_2
04022022_3
04022022_4

Construction progress of the Central Hills Residential Complex for January 28

🏗️ Building 1
• Electricity connection for the first stage of construction of building #1, sections 1-3;

• Fences were installed around the construction site for safe construction;

• Repair work in the sales department has been completed for a comfortable stay of investors at the construction site.

• Concreting of vertical structures (pylons, walls) is in progress, and work is underway to install the floor slab on the 26th floor.

• Bricklaying of internal walls and partitions on 3.4 floors is being carried out.

• Installation of prefabricated reinforced concrete structures (ventilation blocks and staircases) is in progress