We know you've been waiting for our reports, so today we're excited to share with you the results of the work week at the CENTRAL HILLS construction site.
🏗️In building 2:
• Preparations are being made for reinforcing the frames of the vertical structures of the 4th floor.
• The floor slab of the 3rd floor is 100% completed.
🏗️In building 3:
• Installation of beams of the staircase between the 24th and 25th floors is in progress.
• Installation of beams and staircases on the 23rd floor has been completed.
• Masonry of internal room partitions, technical passages of engineering networks on 11 is being carried out floor