Construction progress of the Central Hills RC as of July 26, 2024
Construction progress of the Central Hills residential complex as of July 26, 2024
🏢Slate Tower
• Concreting of the vertical structures of the 9th floor has been completed.
• The arrangement of formwork and reinforcement of the floor slab has been completed by 50%.