Construction progress of the Central Hills RC as of October 25, 2024
Construction progress of the Central Hills residential complex as of October 25, 2024
🏢Slate Tower
• 50% reinforcement of the floor of the 11th floor has been completed.
• Concreting of the floor of the 11th floor is in progress.
🏢Ruby Tower
• Holes are being punched in ventilation units on floors 11-20.
For more information, contact the number: