Progress of construction of the Central Hills residential complex as of July 28, 2025

Progress of construction of the Central Hills residential complex as of July 28, 2025

🏢Slate Tower
• Work is underway to install formwork for reinforcing the second half of the 14th floor slab.

🏢Ruby Tower
• Window installation work is underway on the 10th, 11th, and 12th floors.
• Work is underway on the bricklaying of the interior walls on the 21st floor.