Construction progress of the Central Hills RC as of May 24, 2024
Construction progress of the Central Hills residential complex as of May 24, 2024
🏠 Building № 2
• Reinforcement of the second part of the floor slab of the 8th floor.
• Reception, unloading and storage of fittings.
🏠 Building №3
• Concreting of vertical elements of the stairwell and wall on the 27th floor.