Construction progress of the Central Hills RC as of June 21, 2024

Construction progress of the Central Hills residential complex as of June 21, 2024

🏢Slate Tower
• Reinforcement of vertical structures (walls and pylons) is being carried out.
• Preparation for the installation of formwork is being carried out.