Construction progress of the Central Hills RC as of February 20, 2025

Construction progress of the Central Hills residential complex as of February 20, 2025

🏢Slate Tower
• Concreting of the floor of the 12th floor is in progress.
• Binding of frames of vertical elements of the 12th floor is underway.