Construction progress of the Central Hills RC as of August 2, 2024
Construction progress of the Central Hills residential complex as of August 2, 2024
🏢Slate Tower
• Concreting of the floor of the 10th floor is underway.
• The arrangement of formwork and the binding of the floor slab is being completed.