Construction progress of the Central Hills RC as of July 19, 2024
Construction progress of the Central Hills residential complex as of July 19, 2024
🏢Slate Tower
• Concreting of the vertical structures of the 9th floor is being completed.
• Installation of the floor formwork of the 10th floor is in progress.