Construction progress of the Central Hills RC as of October 18, 2024

Construction progress of the Central Hills residential complex as of October 18, 2024

🏢Slate Tower
• Formwork is being set up and fittings are being delivered to reinforce the floor of the 11th floor.

🏢Ruby Tower
• Holes are being punched in the ventilation units from the 2nd to the 10th floor