Construction progress as of 01/18/2022

🏗️ Building 3
• Concreting of vertical structures (pylons, walls) is in progress, and work is underway to install the floor slab on the 26th floor.
• Bricklaying of internal walls and partitions on 3.4 floors is being carried out.
• In progress works on the installation of prefabricated reinforced concrete structures (ventilation blocks and staircases).

Repair work in the sales department has been completed for a comfortable stay of investors at the construction site.