Construction progress of the Central Hills RC as of May 17, 2024

Construction progress of the Central Hills RC as of May 17, 2024

🏠 Building № 2
• Preparation for concreting the floor slab of the 8th floor.
• Concreting part of the floor slab.

🏠 Building №3
• Concreting of vertical elements of the stairwell and walls on the last 27th floor.