Construction progress of the Central Hills RC as of November 16, 2024

Construction progress of the Central Hills residential complex as of November 16, 2024

🏢Slate Tower
• Slab reinforcement completed.
• Concreting of the floor of the 11th floor is being completed.
• Preparation for reinforcement of vertical structures of the 11th floor is underway.

For more information, contact the number:
+380987005700