Central Hills' traditional weekly construction report.
As of 14.07:
🏗️Building 2
• Installation of the formwork of the floor slab above the 3rd floor.
• Installation of armoframes for the floor slab above the 3rd floor.
• Installation of the beam frames of the floor slab above the 3rd floor.
• Dismantling of the formwork of vertical elements 4 floor
🏗️Building 3
• Masonry of internal walls on the 11th floor continues.