Progress of construction of the Central Hills residential complex as of August 14, 2025

Progress of construction of the Central Hills residential complex as of August 14, 2025

🏢Slate Tower
• Reinforcement and concreting of walls and pylons on the 14th floor.

🏢Ruby Tower
• Bricklaying of interior walls on the 21st floor.
• Sealing of windows and installation of double-glazed windows on floors 10–12.
• Preparatory work for the installation of window frames on floors 13–14.