Construction progress of the Central Hills RC as of March 14, 2024
Construction progress of the Central Hills residential complex as of March 14, 2024
🏠 Building №2:
• Installation of frames of vertical elements of the 7th floor.
•Partial concreting of vertical elements of the 7th floor.
Installation of ventilation units on the second and third floors.