October 13, 2023

Back

yzobrazhenye_2023-10-17_133212718
yzobrazhenye_2023-10-17_133223846
yzobrazhenye_2023-10-17_133231723
yzobrazhenye_2023-10-17_133241212
yzobrazhenye_2023-10-17_133250815
yzobrazhenye_2023-10-17_133305389
yzobrazhenye_2023-10-17_133148807
yzobrazhenye_2023-10-17_133155746
yzobrazhenye_2023-10-17_133202902

We hasten to share with you the results of the work week at the CENTRAL HILLS construction site.

3rd building, 26th floor: 30% of the floor slab has been concreted, reinforcement of the slab is in progress.

3rd building, 15th floor: completion of masonry of internal partitions.

2nd building, 4th floor: reinforcement of vertical elements and reception of concrete.

You can find out details about the project by phone: +380987005700