We hasten to share with you the results of the work week at the CENTRAL HILLS construction site.
3rd building, 26th floor: 30% of the floor slab has been concreted, reinforcement of the slab is in progress.
3rd building, 15th floor: completion of masonry of internal partitions.
2nd building, 4th floor: reinforcement of vertical elements and reception of concrete.