Construction progress of the Central Hills RC as of August 13, 2024

Construction progress of the Central Hills residential complex as of August 13, 2024

🏢Slate Tower
• The formwork is being dismantled.
• Reinforcement of the floor slab has been completed.
• Preparation for concreting is underway.