Progress of construction of the Central Hills residential complex as of September 12, 2025

Progress of construction of the Central Hills residential complex as of September 12, 2025

🏢 Ruby Tower
• Window frames installed on floors 17–18.
• Preparations underway for bricklaying of interior walls on floor 22.

🏢 Slate Tower
• Concrete pouring of the 15th floor slab is underway.
• Work is underway to install ventilation units.