Progress of construction of the Central Hills RC as of 12 May 2025

Progress of construction of the Central Hills residential complex as of 12 May 2025

🏢Slate Tower
• Concrete work is being carried out on the 13th floor.

🏢Ruby Tower
• Sealing of mounting foam in window openings on the 8th and 9th floors is underway.