Construction progress of the Central Hills RC as of July 12, 2024

Construction progress of the Central Hills residential complex as of July 12, 2024

🏢Slate Tower
• The walls and pylons of the 9th floor are being concreted.
• The floor formwork of the 10th floor is being installed.

For more information, contact the number: