Construction progress of the Central Hills RC as of April 12, 2024

Construction progress of the Central Hills residential complex as of April 12, 2024

🏠 Building №2:
• Installation of vertical elements of the 8th floor.
• Concreting of the walls and pylons of the 8th floor.