Construction progress of the Central Hills RC as of November 14, 2023

🏠 Building №2:
• Formwork for the floor slab of the 4th floor is being installed.

🏠 Building № 3:
• Dismantling of the floor slab formwork on the 27th floor is underway.
• Masonry of internal walls and partitions on the 17th floor is in progress.