Construction progress of the Central Hills RC as of April 11, 2025

Construction progress of the Central Hills RC as of April 11, 2025

🏢Ruby Tower
• Preparations are underway for the installation of windows on floors 8-9.
• Masonry of the interior walls of the 18th floor has been completed.
• Masonry of the interior walls of the 19th floor is underway.