Recent achievements at the construction site 🏗️ CENTRAL HILLS residential complex:

• Preparation of openings for installation of ventilation units on the 14th and 15th floors of the 3rd building.

• Masonry of internal partitions on the 13th floor.

• Installation of ventilation units on floors 17-23.