Construction progress of the Central Hills RC as of November 1, 2024

Construction progress of the Central Hills residential complex as of November 1, 2024

🏢Slate Tower
• Dismantling and installation of formwork for reinforcement and concreting of the second half of the floor of the 11th floor is underway.
• Frames of vertical elements of the 11th floor are being prepared.

🏢Ruby Tower
• Holes are being punched in ventilation units on floors 21-26.