Back
Construction progress of the Central Hills RC as of March 1, 2024
Construction progress of the Central Hills residential complex as of March 1, 2024
🏠 Building № 2:
• Arrangement of the concrete mixture of the floor slab of the 6th floor.
• Reinforcement of the vertical structures of the 7th floor and preparation for their installation is underway.
For more information, contact the number:
+380987005700